Facility Optimization - Step 2
Identify, analyze, and quantify enhancement opportunities

In Step 2, we will identify, analyze, and quantify enhancement opportunities for the facility based on the field-test data and observations. Our broad experience and knowledge of best practices makes this process effective and meaningful.

Each enhancement opportunity will be evaluated and analyzed to identify its' operational and financial impact. Where applicable, more detailed engineering and economic analysis is performed. Once the enhancement recommendations are evaluated, they will be sorted into three tiers.

Tier 1: Implement immediately - economic value fully quantifiable.

Tier 2: Further investication in the next budget cycle.

Tier 3: General recommendations with hard to quantify benefits.

  Annual Revenue or
Cost Savings ($)
Required
Capital or O&M
Cost ($)
5-Year NPV($) Simple
Payback
Period(years)
Tier 1 $117,009 $159,000 $567,314 1.36 years
Tier 2 $450,796 $500,000 $1,598,013 1.11 years
Total $567,805 $659,000 $1,921,932 1.16 years